Division of Campus Affairs
Facilities Management Services
TO: All Facilities Coordinators, College of Fine Arts and Shutdown Group
FROM: Service Response Center
DATE: June 12, 2013
SUBJECT: Concrete Sidewalk Work South and East MMCH 6/12- through 6/20
Concrete sidewalk work is scheduled to occur on the east side of Margaret Morrison Carnegie Hall June 12 through June 20. This is the walkway down towards the rear of the building.
There is also work on the south side of the building along Margaret Morrison Street adjacent the stop sign that will begin on Monday, June 13 through June 20, this work includes sidewalk and curbing.
Please pay attention to the signage that closes these sections of sidewalk during this work.
If you have any questions please contact Kyle Tomer at 8-6332 or e-mail kt2n@andrew.cmu.edu.
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Kyle K. Tomer
Associate Director of FMS for Client Services
Facilities Management Services
Carnegie Mellon University
412-268-6332