TO:   All Facilities Coordinators and Shutdown Group

FROM:  Service Response Center

DATE:  July 8, 2013

SUBJECT: Kraus Campo Walkway Recoating 7/9 through 7/30

 

Recoating of the Kraus Campo Orange Walkway is currently scheduled for 7-9-13 through 7-30-13.  The coating process will occur in several sections at a time and the work areas will be closed to all pedestrian traffic during the work.

 Please pay attention to the areas that will be closed off.

 

The work will begin with grinding of the existing coating and applying the new coating in 3 separate coating stages.  There will be an odor on the final clear coating stage. 

This work is all exterior and work dates will change depending on the weather. The initial stage of coating is scheduled for 7/12, 7/13, and 7/14 again depending on clear weather.

 

If there are any questions please contact Kyle Tomer, 412-268-6332 or e-mail kt2n@andrew.cmu.edu.

 

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Kyle K. Tomer

Associate Director of FMS for Client Services

Facilities Management Services

Carnegie Mellon University

412-268-6332

kt2n@andrew.cmu.edu