TO: All Facility Coordinators and Shutdown Group
FROM: Service Response Center
DATE: July 15, 2013
SUBJECT: Masonry Repairs Wean Hall Starts 7/15/2013 – 11/2013
Turner Construction and Mariani & Richards have begun making concrete repairs to the exterior walls of Wean Hall. The work includes cutting out areas where the concrete is spalling. There will be noise from the concrete saw and chipping in preparation to the patching.
Work is starting at the west end of the south elevation and the west elevation in coordination with the construction of the new Scott Hall building. It is intended to then continue this repair work along the south elevation as weather permits and anticipated to be completed by November, 2013.
Updates will be issued monthly as work progresses.
Please direct any questions or concerns to Ed Hydzik, eh0x@andrew.cmu.edu.
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~