On Thursday, July 25, at 10:00 AM there will be a required safety load test on the emergency generator serving Carnegie Mellon University‘s 300 South Craig Building. 

Cummins is scheduled to perform the annual maintenance and conduct a load bank test on the emergency generator. The contactor will start running the generator at 10:00AM for about 30 minutes in preparation for the annual maintenance.

Once the annual maintenance is complete, the generator will run for about two hours to conduct the load bank test.

 

The test occurs in the building parking lot and will create much noise for the surrounding area. We anticipate completing all of the work by 3:00pm.

If you have any questions please call Kyle Tomer at 8-6332 or e-mail kt2n@andrew.cmu.edu .

 

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Kyle K. Tomer

Associate Director of FMS for Client Services

Facilities Management Services

Carnegie Mellon University

412-268-6332