Fri. Mar 29th, 2024

Division of Campus Affairs

Facilities Management Services

 

TO: All Facilities Coordinators and Shutdown Group

FROM:  Service Response Center

DATE:  July 31, 2013

SUBJECT: Tennis Court Repairs 8/5 through 8/23

 

Tennis court repairs and re-coating is scheduled to occur between 8-5-13 and be completed by 8-23-13.

The courts will be closed during this work as each court has cracks that require repair and the overall surface will be re-coated.

Rain will cause delays in this work but there have been days permitted in the schedule to accommodate some rain activity.

The nets will be taken down during this work as well.

Please stay off the tennis courts until work is completed.

 

If you have any questions please contact Kyle Tomer at 8-6332 or e-mail kt2n@andrew.cmu.edu.

 

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Kyle K. Tomer

Associate Director of FMS for Client Services

Facilities Management Services

Carnegie Mellon University

412-268-6332

kt2n@andrew.cmu.edu