SUBJECT: Tennis Court Repairs 8/5 through 8/23
Tennis court repairs and re-coating is scheduled to occur between 8-5-13 and be completed by 8-23-13.
The courts will be closed during this work as each court has cracks that require repair and the overall surface will be re-coated.
Rain will cause delays in this work but there have been days permitted in the schedule to accommodate some rain activity.
The nets will be taken down during this work as well.
Please stay off the tennis courts until work is completed.