SUBJECT: CFA Parking Lot ADA Curb Cut 9/18
Eisler Landscape Contractor will install an additional ADA curb cut on Wednesday, September 18, just inside the lift gate of the College of Fine Arts parking lot.
The noisy demolition work will happen from 7:00 AM to 9:00 AM and then the concrete pour from 1:00 PM to 3:00 PM.
This is in preparation to temporarily block off part of the sidewalk by Margaret Morrison Carnegie Hall for hauling dirt and materials for the new garden installation.
Please direct any questions or concerns to Ed Hydzik, eh0x@andrew.cmu.edu.
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Kyle K. Tomer
Associate Director of FMS for Client Services
Facilities Management Services
Carnegie Mellon University
412-268-6332