TO: UC, Purnell Center, Wean Hall and Doherty Hall Facility Coordinators and Shutdown Group
FROM: Service Response Center
DATE: November 6, 2013
SUBJECT: Elevator Load testing for UC, Purnell, Wean, and Doherty Halls, 11/12 – 11/14
FMS elevator contractor is to perform the state mandated tests for the following buildings on November 12, 13 and 14.
The full load at Wean/Doherty (Otis MRL) is scheduled for 8 AM on November 14th (8 AM to 1:00 PM)
Purnell: 3 PRV are scheduled for Afternoon of November 13th (1 PM – 5:00 PM)
University Center: 5 PRV scheduled for November 12th (8 AM – 3 PM).
One elevator will be down at a time.
If you have any questions please contact Kyle Tomer at 8-6332 or kt2n@andrew.cmu.edu .
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Kyle K. Tomer
Associate Director of FMS for Client Services
Facilities Management Services
Carnegie Mellon University
412-268-6332