TO:    Doherty Hall  and Mellon Institute Facility Coordinators and Shutdown Group

FROM:  Service Response Center

DATE:  December 2, 2013

SUBJECT: Elevator Load testing for Mellon Institute and Doherty Halls, 12/10 + 12/11

 

FMS elevator contractor is to perform the state mandated  Full Load tests for the following buildings on December 10 and 11.

 

Doherty Hall MRL elevator #9 at the front of the building Phase II December 10 at 8:00AM will probably be 4 hours

 

Mellon Institute #1 Left Passenger elevator December 10 12:00PM will probably be 4 hours

 

 

Mellon Institute #2 Right Passenger elevator December 11 8:00AM will probably be 4 hours

 

 

Mellon Institute #3  Passenger / Freight elevator December 11 12:00PM will probably be 4 hours

 

One elevator will be down at a time.

If you have any questions please contact Kyle Tomer at 8-6332 or kt2n@andrew.cmu.edu .

 

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

Kyle K. Tomer

Associate Director of FMS for Client Services

Facilities Management Services

Carnegie Mellon University

412-268-6332