Update:
Doherty Hall Rooms affected by flooding.
Since the flood occurred on the C level, rooms on the C were generally affected by water on the floor. The rooms below on the D level were flooded from above and water on the floor.
C Level Rooms: 311, 312, 313, 314, 315, 316, 316A.
D Level Rooms: 312, 313, 314, 315A, 315B, 316.
From: FMS Announce
Sent: Thursday, December 26, 2013 2:28 PM
To: ‘post+cmu.fms.announce@andrew.cmu.edu‘; fms-cfa@lists.andrew.cmu.edu; fms-doherty@lists.andrew.cmu.edu; fms-shutdown@lists.andrew.cmu.edu
Subject: Doherty Hall Frozen Water Line Flood 12/26
Division of Campus Affairs
Facilities Management Services
TO: Doherty Hall Facility Coordinators and Shutdown Group
FROM: Service Response Center
DATE: December 26, 2013
Subject: Doherty Hall Frozen Water Line Flood 12/26
A frozen water line flooding C and D Level of Doherty Hall was discovered today, December 26. The location of the frozen pipe is C314, FMS and Advance Restoration are on sight cleaning and making repairs.
If you have any questions, contact the Service Response Center at 412-268-2910 or write to fixit@andrew.cmu.edu.
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Kyle K. Tomer
Associate Director of FMS for Client Services
Facilities Management Services
Carnegie Mellon University
412-268-6332