1/23 UPDATE – Electric Restoration to Normal System Operation at 6:00 AM on 1/23/14.  Repairs have been made to all damaged equipment.  Duquesne Light will   be switching main campus electric service to its normal configuration tomorrow morning.  We expect this to be invisible to people and systems receiving electric service.  However, FMS will have additional  personnel on hand to respond should the transfer not   go as expected.  
Division of Campus Affairs
Facilities Management Services
TO:       ALL Facility Coordinators and Shutdown Group and select building shutdown groups
FROM:  Service Response Center
DATE:  January  8, 2014
SUBJECT:   Major Electric and Chilled Water Failure on Main Campus
At 1:15 AM today  Electric Power was lost to the following buildings:  Hamerschlag Hall, Newell Simon Hall,  Smith Hall, Doherty Hall, Gates-Hillman Center,  Hamburg Hall,  Roberts Hall, Scaife Hall and the FMS Building.  As a result of this power loss, all  Chilled Water to ALL main campus buildings was also lost.  FMS crews and Duquesne Light are currently working to restore power to the extent possible and then restore chilled water.
If you have any questions, contact Martin Altschul, 8-2529 or e-mail  ma3q@andrew.cmu.edu.
Martin H. Altschul, PE
University Engineer
Facilities Management Services
Carnegie Mellon University
5000 Forbes Avenue
Pittsburgh, PA 15213
Phone: (412) 268-2529