FMS- Mandatory Actions to Prevent Freeze Damage
TO: All Facility Coordinators and Shutdown Group FROM: Service Response Center DATE: January 27, 2014 SUBJECT: Mandatory Actions to Prevent Freeze Damage Over the few days, we…
TO: All Facility Coordinators and Shutdown Group FROM: Service Response Center DATE: January 27, 2014 SUBJECT: Mandatory Actions to Prevent Freeze Damage Over the few days, we…
TO: GSIA, Posner Center, and Posner Hall, East Campus Garage, Hamburg Hall, Smith Hall, 6555 Penn Ave, 407-407 South Craig Street, 4615 Forbes and Shutdown Group FROM: Environmental Health…
Division of Campus Affairs Facilities Management Services TO: Wean Hall and Doherty Hall Facility Coordinators and Shutdown Group FROM: Service Response Center DATE: January 27, 2014 SUBJECT: Wean…
TO: Hunt, Porter, Baker, College of Fine Arts, Margaret Morrison Carnegie Hall, Gates Hillman Center, 300 SCraig St, Skibo Gym and Shutdown Group FROM: Environmental Health and Safety DATE: …
Division of Campus Affairs Facilities Management Services TO: College of Fine Arts Facility Coordinators and Shutdown Group FROM: Service Response Center DATE: January 24, 2014 SUBJECT: CFA Passenger Elevator…
FINAL UPDATE – Main Campus substation was returned to normal configuration at 6:00 AM this morning with no interruption to service. Please be advised that future building load transfers…
Division of Campus Affairs Facilities Management Services TO: ALL Facility Coordinators and Shutdown Group FROM: Service Response Center DATE: January 22, 2014 SUBJECT: S Neville St closure starting at 9:00…
1/23 UPDATE – Electric Restoration to Normal System Operation at 6:00 AM on 1/23/14. Repairs have been made to all damaged equipment. Duquesne Light will be switching main campus electric…
TO: All Facility Coordinators and Shutdown Group FROM: Service Response Center DATE: January 21, 2014 SUBJECT: Mandatory Actions to Prevent Freeze Damage Over the next 60…