TO: All Facility Coordinators and Shutdown Group
FROM: Service Response Center
DATE: February 7, 2014
SUBJECT: Scott Hall Concrete Pour and Heavy Construction Traffic- 2/13
On Thursday, February 13, contractors will be pouring and pumping 200 cubic yards of concrete for Scott Hall. This 200 CY pour is the for the Scott Hall center core foundations where the old salt storage area was located.
The pump truck will be set up at west side of Wean Hall in the construction site. The trucks are scheduled to deliver 10 yard loads every 15 minutes from Neville Street through the CIC building and up Hamerschlag Drive past the FMS building.
They will stage two at a time at the Wean/Doherty loading dock.
This additional road traffic through the CIC Parking Garage onto Hamerschlag Drive near Facilities Management Building can be expected between 7 AM – 3 PM.
Please use caution if driving through Neville, the CIC Parking Garage, and Hamerschlag Drive.
If you have any questions please contact Maxim Dorosa at 8-8936 or maxd@andrew.cmu.edu .
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~