TO: All Facility Coordinators and Shutdown Group
FROM: Service Response Center
DATE: February 27, 2014
SUBJECT: 30 Campus and Housing Buildings Power Shutdown Schedule for Spring Break
Due to the damage to high voltage circuits by the construction incident on 11/15/13, transfer of power to back-up cables is needed to make repairs.
Main campus and housing buildings will have a power interruption for approximately 15 between the hours of 5:30 AM until 7:00 AM on scheduled dates
Monday – March 10, 2014 5:30 AM – 7:00 AM
Boss, McGill, Scobell, Welch
Margaret Morrison Apartments
Margaret Morrison Storefronts
Henderson Hall
Hamerschlag House
Donner Hall
Resnik and West Wing Dormitories
Skibo Gym
Margaret Morrison Carnegie Hall
Tuesday March 11, 2014 5:30 AM – 7:00 AM
Roberts Engineering Hall
Scaife Hall
Hamerschlag Hall
Porter Hall
Baker Hall
Hunt Library
College of Fine Arts
Cyert Hall
Wednesday March 12, 2014 5:30 AM – 7:00 AM
University Center
East Campus Parking Garage
Warner Hall
GSIA, Posner Hall and Posner Center
Purnell Center
Gates Hillman Center
Thursday March 13, 2014 5:30 AM – 7:00 AM
Wean Hall
Doherty Hall
Facilities Management Services has plan this power interruption of 15 minutes/ building to replace the damaged cables on the WEH3-19 . If you have any questions please e-mail or phone Kyle Tomer kt2n@andrew.cmu.edu, 8-6332 and Steve Guenther sgue@andrew.cmu.edu, 8-4948 .
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Kyle K. Tomer
Associate Director of FMS for Client Services
Facilities Management Services
Carnegie Mellon University
412-268-6332