Subject: Wean Hall Shutdown – Transfer of Power 9/21-9/22

 

Division of Campus Affairs

Facilities Management Services

 

TO:   Shutdown Group, Wean Hall

FROM:  Service Response Center

DATE:  September 14, 2015

SUBJECT: Wean Hall Shutdown – Transfer of Power 9/21-9/22

 

FMS Electricians will be transferring power at Wean Hall on Monday, 9/21, at 11:00PM through Tuesday, 9/22, at 7:00AM.  This shutdown is required to tie in the transformers for the new Scott Hall clean room.  Below is a schedule of when the transfers will take place:

 

          At 11:30PM (Monday 9/21) we will be transferring power from one circuit to another circuit.  The power will be interrupted for about 30 minutes or less.

          At 2:30AM (Tuesday 9/22) we will be transferring power from one circuit to the original circuit. Once again, power will be interrupted for about 30 minutes or less.  

          At 5:30AM (Tuesday 9/22) we will be balancing the loads  between the 2 circuits.  During this, power will be interrupted for about 30 minutes or less.

 

As we get closer, we should have a better idea of which areas will be affected for each transfer.

 

If you have any questions about this shutdown, contact the Service Response Center at X2910 or fixit@andrew.cmu.edu.