UPDATE: CDFD may be bringing the chiller and towers in on Friday, 1/20. 

 

If they do come on Friday, several large trucks will be coming in through CIC and parking at the Roberts loading dock.  The road will remain open during this, but there may be intermittent traffic slowdowns. 

 

From: FMS Announce
Sent: Tuesday, January 17, 2017 11:05 AM
To: ‘fms-shutdown@lists.andrew.cmu.edu’; ‘fms-fmsb@lists.andrew.cmu.edu’; ‘fms-wean@lists.andrew.cmu.edu’; ‘fms-gates@lists.andrew.cmu.edu’
Subject: Delivery and Setting of FMS Chiller and Cooling Tower 1/21

 

Division of Operations

Facilities Management Services

 

TO:  Shutdown Group, FMS Building, Wean Hall, Gates

FROM:  Service Response Center

SUBJECT: Delivery and Setting of FMS Chiller and Cooling Tower 1/21

 

The delivery and setting of the FMS Chiller #1 and Cooling Tower #5 is scheduled for Saturday, January 21, 2017 weather permitting.

 

The chiller and the tower will arrive at 7:00AM and will require intermittent blocking of the lower Hamerschlag Drive by FMS all day.  This may impact your access to Wean Hall and the Gates Garage when CDFD is lifting over the roadway.  These lifts will be at ½ hour intervals several times during the day.

 

Access to Wean Hall and Gates Garage will not be impacted from Frew Street.

 

Questions should be directed to the Project Manager, Max Dorosa, at maxd@andrew.cmu.edu.