The project is phased as indicated below:

Friday, 3/10 : Delivery and Unloading of Windows on Site/ CFA East Face Windows Install

3/13 – 3/15 :   CFA North Face Windows Install

3/16 – 3/17:  CFA West Face Windows Install

 

Signage will be posted redirecting pedestrian traffic during each phase of the install.  In addition, Volpatt Construction tradesmen will be present to redirect pedestrian traffic.

 

Dust and noise will be maintained at a minimum during this time.

 