SUBJECT: Tepper Project – Forbes Ave Lane Closure and Morewood Parking Lot Closure 5/25
Beginning May 25th, the Tepper Project will be closing the Westbound curb lane of Forbes Avenue and the adjacent sidewalk from Morewood Avenue to the traffic signal at Hamburg Hall. The Morewood Parking Lot will also be closed for the summer to accommodate the adjacent construction and repaving the lot.
Forbes Avenue:
Phase 1 – May 25th to July 28th – Work from Morewood Avenue to the traffic signal at Hamburg Hall. The existing inbound bus stop on Forbes Avenue, West of Morewood Avenue, will be combined with the existing inbound Forbes Avenue bus stop at the traffic signal opposite Hamburg Hall.
Phase 2 – July 28th to April 13th – Reopen bus stop West of Morewood. Close bus stop at Hamburg Hall. Continued lane and sidewalk closure.
Morewood Parking Lot: Closed to Parking on May 25th. Accessible for access and dropoff via Morewood Avenue TWO WAY drive.
Phase A – May 25th to June 16th – Tepper Quad site work. Site work in front of Devonshire (pedestrians to use WQED). Southern portion of internal sidewalk (in yellow).
Phase B – June 19th to July 7th – Site Work at WQED access (Pedestrians to use Devonshire). Northern portion of internal sidewalk (in purple)
Phase C – Mid July to August – Paving Morewood lot as weather allows.
See attached PDF’s that illustrate the limits of work.
If there are any questions, please contact CDFD Project Manager Mike Kelley at 412-268-2366.
Forbes-Phase-1-2-03.03.17.pdf
Morewood-Phase-A-B-03.3.17.pdf