UPDATE:  Pedestrian access from the CIC Garage to Neville Street will be maintained at all times.

 

 

From: FMS Announce
Sent: Friday, May 26, 2017 1:42 PM
To: fms-shutdown@lists.andrew.cmu.edu; fms-cic@lists.andrew.cmu.edu; fms-ppb@lists.andrew.cmu.edu; fmsfcc-all@lists.andrew.cmu.edu
Subject: Construction Impact to CIC Garage and Hamerschlag Drive Access Begins Tuesday May 30th

 

Division of Operations

Facilities Management and Campus Services

 

TO:  Shutdown Group, CIC group, Physical Plant building group, All Facility Coordinators

FROM:  Service Response Center

DATE:  May 26, 2017

SUBJECT: Construction Impact to CIC Garage and Hamerschlag Drive Access Begins Tuesday May 30th

 

Beginning Tuesday May 30th at 6:00am, contractors will be installing a new electric ductbank in the CIC garage.  During Phase #1, there will be NO access from Neville Street.  All access to Hamerschlag Drive and the CIC garage must enter from the Frew Street Entrance.

 

This is a five phase project that will be in effect through June 20th.  There will be no through traffic through the CIC garage for phases #1 through #4.  There will be no vehicular access to FMS during phases #4 and #5.

 

See attached logistics plans for all 5 phases.  These phases include the anticipated dates and may be revised if progress improves or worsens.  An update will be issued as each new phase commences.

 

If you have any questions or concerns, please call CDFD Project Manager, Mike Kelley at 412-268-2366 or email mdkelley@andrew.cmu.edu.