TO:  Shutdown Group, CIC group, All Facility Coordinators

FROM:  Service Response Center

DATE:  June 9, 2017

SUBJECT: Construction Impact to CIC Garage  and Hamerschlag Drive 6/9/17 UPDATE


Beginning on Monday, June 12th, at 6:00AM, Work begins on Phases 2 and 3 for the new electric ductbank in the CIC garage.  Vehicular access to the CIC garage will need to enter from the Neville Street Entrance and use the upper ramp.  Pedestrian access from the CIC garage to Neville Street will be maintained at all times

 

Vehicular access from Neville Street will continue to be restricted THROUGH the lower level of the CIC GarageVehicular traffic will NOT be able to continue through the garage to Hamerschlag Drive, so all through vehicular traffic that is accessing the Gates Garage, FMS, or any other locations along Hamerschlag Drive will still need to enter via Frew Street.

 

Beginning on Wednesday June 14th, there will be limited access for deliveries to the CIC loading dock and FMS once manhole excavation begins on Wednesday.  Those responsible for deliveries should review the access restrictions prior to scheduling deliveries.

 

Work is anticipated to be completed by Friday June 16th.

 

See attached with updated graphics for additional information.

 

If you have any questions or concerns, please call CDFD Project Manager, Mike Kelley at 412-268-2366 or email mdkelley@andrew.cmu.edu.