Division of Operations
Facilities Management and Campus Services
TO: Shutdown Group, Housing, Morewood Gardens
FROM: Service Response Center
DATE: June 27, 2017
SUBJECT: Morewood Garden Electrical shutdown 6/29
There will be an electrical shutdown at Morewood Gardens, Morewood E Tower, the Underground, the Cyert Center and Stever House on Thursday, 6/29, starting at 6:00PM and continuing until 4:00AM on 6/30. This shutdown is necessary in order to upgrade the electrical service to the building.
Morewood Gardens, Morewood E Tower, The Underground, and Cyert Center will not have any power during this time. Stever House will have temporary power provided by a generator, but will not have cooling. All services will be restored by 6:00AM on 6/30.
If you have any questions or concerns, please contact Janice Held at 412-527-5627 or jheld@cmu.edu.