Facilities Management and Campus Services
TO: Shutdown Group, Warner group
FROM: Service Response Center
DATE: August 3, 2017
SUBJECT: Warner Hall A-Level Mechanical Work 8/5/17
HVAC contractors will be repairing insulation on the Warner Hall A-Level mechanical systems on Saturday, August 5th from 6:00AM to 4:30 PM. There will be no interruptions in HVAC service – however contractors will be working above ceilings in the areas of work identified on the attached floor plan. If the planning work is not completed on Saturday, any remaining work will be finished first thing on Monday, August 7th before the building is occupied.
Please contact Jennifer McDowell at jmdowell@andrew.cmu.edu or x8-3763 if you have any questions or concerns.
2017-8-5-WH-A-Level-Mechanical-Work.pdf