Facilities Management and Campus Services
TO: Shutdown Group, All Facility Coordinators
FROM: Service Response Center
DATE: August 17, 2017
SUBJECT: Construction Update – Tepper Project – South Neville Traffic Plan – 8/17
There will be daytime lane restrictions on South Neville Street beginning today, 8/17, as contractors connect the Tepper Project to the City storm water system.
South Neville Street will be down to one open lane with flaggers providing alternate directional flow from the hours of 7:00AM to 3:30PM.
Both lanes will be open during off hours with steel plates on the road for the duration of the project. It is anticipated that the work will be completed by 9/1.
Please see the attached graphic that illustrates the location of the work.
If there are any questions or concerns, please contact CDFD Project Manager, Mike Kelley, at mdkelley@andrew.cmu.edu or at 412-268-2366.
S-Neville-MPT-version-2-phase-2.pdf