UPDATE – The concrete pour at GSIA is now scheduled to start at 5:00AM tomorrow, 9/7.
The concrete trucks will arrive in 20-30 minute intervals on Frew Street at the sidewalk between the Peace Garden and Hunt Library. Attached is a modified site plan showing the route the trucks will take.
There will be a concrete pumper parked on the sidewalk between the steps on the South side of CFA and the Peace Garden. The Pumper will be coned and taped off.
Flaggers will be present to direct pedestrian traffic and help guide the truck.
This work is expected to be completed by 7:00AM
For questions regarding the concrete delivery and the above schedule, please contact Steve Morgan, CDFD Project Manager, at 304-830-2061.
From: FMS Announce
Sent: Tuesday, September 4, 2018 10:06 AM
To: ‘fms-shutdown@lists.andrew.cmu.edu’ <fms-shutdown@lists.andrew.cmu.edu>; ‘fms-gsia@lists.andrew.cmu.edu’ <fms-gsia@lists.andrew.cmu.edu>; ‘fms-hunt@lists.andrew.cmu.edu’ <fms-hunt@lists.andrew.cmu.edu>; ‘fms-cfa@lists.andrew.cmu.edu’ <fms-cfa@lists.andrew.cmu.edu>
Subject: GSIA Concrete Delivery 9/7
Division of Operations
Facilities Management and Campus Services
TO: Shutdown Group, GSIA, Hunt library, CFA
FROM: Service Response Center
SUBJECT: GSIA Concrete Delivery 9/7
Concrete is scheduled to be delivered to the Cooper-Simon Auditorium in GSIA on Friday, 9/7, starting at 6AM. There will be 4 deliveries at 30 minute intervals.
The attached map will show the route the trucks will be taking in order to make the delivery. Flaggers will be present to direct pedestrian traffic and help guide the truck.
There will be noise during this work due to the backup alarms on the trucks.
For questions regarding the concrete delivery, please contact Steve Morgan, CDFD Project Manager, at 304-830-2061.
Cooper-Simon-Concrete-Placement-Site-Impacts-REVISED.pdf