TO: Shutdown Group,

FROM:  Service Response Center

SUBJECT: GATF Sanitary Line Work Starting 10/22

 

The TCS Project mechanical contractor will be modifying a sanitary line on Level 1 of the GATF building starting on Monday, 10/22.  Work will be limited to Suite 123 (ERM), Suite 122 (currently unoccupied), the East end of Corridor 100, closet 115 and mechanical room 114. 

 

During the week of 10/29, the existing sanitary lines will be tied in to the new sanitary line.  This will require that anything tied in to the sanitary line will be tagged so that it is not used when the line is opened up.  This disruption will be limited to one evening shift per outage.

 

These disruptions will be limited to the East half of the building as follows:

3rd floor unisex bathroom across from rooms 334-336.

-3rd floor kitchen sink in room 346.

-3rd floor unisex bathroom next to room 330A.

-2nd floor ROTC garage laundry sink next to freight elevator.

 

This work will all be done during second shift, beginning at 6:00PM. 

 

If there are any questions or concerns regarding this work, please contact CDFD Project Manager, Mike Kelley, at mdkelley@andrew.cmu.edu or 412-268-2366.