Fri. Jan 23rd, 2026

Division of Operations

Facilities Management and Campus Services

 

TO:  Shutdown Group, HOA, Posner Hall, Posner Center

FROM:  Service Response Center

DATE:  August 21, 2019

SUBJECT: Hall of the Arts/Posner Tech Street Lane Modification

 

CDFD will be offloading a transformer for the Hall of the Arts/ Posner Renovation project at the Posner Hall Loading Dock tomorrow, 8/22, starting at 5:00AM.  This should be completed by 8:00AM, but may last longer.    

 

There may be some noise from the forklift back up alarm after 7:00AM.

 

This work will take up the parking lane, as well as the drive lane, on the Posner side.  There will be flaggers onsite to direct traffic.

 

Please contact CDFD Project Manager, Utkarsh Ghildyal, at 412-983-5267 if there are any questions or concerns regarding this work.