Mon. Jan 19th, 2026

Facilities, Infrastructure and Risk Management (FIRM)

Facilities Management & Campus Services

 

TO:  Shutdown group, Wean, Doherty, GHC, Scott,  Hamerschlag Group

FROM:  Service Response Center

DATE:  December 22, 2020

SUBJECT: T-Mobile Crane at Doherty Hall- 12/23/20

 

T–Mobile is working on upgrading their current equipment on top of Doherty Hall to support the 5G upgrade being carried out nationwide. For this endeavor, T Mobile will be bringing a crane on site on 12/23/2020 6:00 A.M. onwards till 3:00 P.M. to lift the equipment on top of Doherty Hall. The crane will be staged on Hamerschlag Drive. Please see attached documents.

Access to Gates Garage will be limited during this time. Emergency vehicular access will remain. Deliveries to Wean and Doherty Hall for the day of 12/23/2020 will be impacted and should be rescheduled.

Please contact Salonika Garapaty sgarapat@andrew.cmu.edu in case of any further questions.