SUBJECT: Fifth Neville Apartment Light Pole installation 3/1
Two light poles will be installed along Fifth Avenue in front of the Fifth Neville Apartments on Monday, 3/1, from 9AM-5PM.
The front entrance to the Fifth Neville apartment building will be closed during this work. The sidewalk and back doors will be accessible.
There will also be a lane closure in front of the apartments. Signage will be placed directing pedestrians to use the South side of Fifth Avenue in front of the Residence on Fifth.
If you have any questions or concerns please contact Jan Held, jheld@cmu.edu, 412 527 5627.