UPDATE – A second coating of the orange walkway will be applied at Kraus Campo on Sunday, 8/15.  This area is currently blocked off for renovation work.

 

There will be an odor related to this work during the coating process.  Please keep the windows on the East side of College of Fine Arts closed during this work.

Outside air dampers at CFA, HOA and Posner Center will also be closed during this work as well.  Please advise staff working in the Hall of Arts/Posner, East face of CFA or CFA A-Level Music spaces on Sunday, 8/15, to either 1) work remotely or 2) contact FMCS for a portable air purifier by calling 412-268-2910.

 

 

 

UPDATE FOR FACILITY COORDINATORS – Please advise staff working in the Hall of Arts/Posner, East face of CFA or CFA A-Level Music spaces to either 1) work remotely or 2) contact FMCS for a portable air purifier by calling 412-268-2910.

 

 

Facilities, Infrastructure and Risk Management (FIRM)

Facilities Management & Campus Services

 

TO:  Shutdown Group, Facility Coordinators; Posner, HOA, CFA

FROM:  Service Response Center

DATE:  August 4, 2021

SUBJECT: Kraus Campo Epoxy Coating Work 8/5 – 8/9

 

The Kraus Campo walkway will be having work done to the epoxy coating starting on 8/5 thru 8/9.  This area is currently blocked off for renovation work.

 

There will be an odor related to this work during the coating process.  Please keep the windows on the East side of the College of Fine Arts closed during this work.  Outside air dampers at Hall of Arts and Posner Center will also be closed.

 

Please contact Ron Cunningham at rcunning@andrew.cmu.edu for any questions or concerns.