Fri. Jan 16th, 2026

Facilities, Infrastructure and Risk Management (FIRM)

Facilities Management & Campus Services

 

TO:  Shutdown Group, Hamerschlag Hall

FROM:  Service Response Center

SUBJECT:  Hamerschlag Hall Chilled Water Shutdown 4/17 – 4/20

 

As part of the utility work related to the construction of Scaife Hall and ongoing work in the Hamerschlag Hall F-Level, the chilled water system in Hamerschlag Hall will be offline beginning late Sunday, 4/17. Work is anticipated to be completed with the system back on line by mid-day Wednesday, 4/20. 


This work is currently planned to coincide with lower outdoor temperatures, so the majority of air systems will be utilizing outdoor air for any cooling. Some interior spaces may experience temperature increases as a result of the shutdown. If there are any concerns for interior spaces please let us know as soon as possible. 

 

Please reach out to Chris Conroy, CDFD Associate Director MEP, at 412-268-3879 (email: cconroy@andrew.cmu.edu), or Jan Held, CDFD Principle Project Manager, at 412-268-1838 (email: jheld@andrew.cmu.edu) with any questions or concerns related to this work.