Facilities, Infrastructure and Risk Management (FIRM)
Facilities Management & Campus Services
TO: Shutdown Group, Warner Hall, Facility Coordinators
FROM: Service Response Center
DATE: July 11, 2022
SUBJECT: Concrete Work Near Warner Hall 7/12 – 7/22
Concrete sidewalk repairs are scheduled to occur along the Forbes Ave corridor from 7/12 thru 7/22 at the walkways adjacent to Warner Hall and the Walking to the Sky statue. This work may include the accessible ramps and stair landings.
Areas of work will be sectioned and occur at separate times to ensure pedestrian access to the mall area is available at all times.
Please contact Jenn Rogers, FMS Project Manager, at jlrogers@andrew.cmu.edu for any questions or concerns regarding this work.