UPDATE – Below is a 2-week look ahead for the work happening on Frew Street.
For any questions or concerns please contact Kevin Shaffer, CDFD Sr. Project Manager, at kevinsha@andrew.cmu.edu or 412-287-2349 or Mike Kelley, CDFD Associate Director of Construction, at mdkelley@andrew.cmu.edu or 412-292-1300.
June 12 – June 16, 2023
· Continue yard storm and water line install
· Duct bank install
· RCP excavation Noise Impact
· Start forming curbs
· Public storm excavation Noise Impact
· Parking closed off in front off in Phase 1A through 6//23 Traffic Impact
· Mobilize and relocate fencing for Phase 1A.
June 19 – June 23, 2023
· Continue street storm demo
· RCP install
· Curb forming
· Sidewalk prep and pour
· Patch Paving
· Parking closed off in front off in Phase 1A through 6/30/23 Traffic Impact
UPDATE – Below is a 2-week look ahead for the work happening on Frew Street.
For any questions or concerns please contact Kevin Shaffer, CDFD Sr. Project Manager, at kevinsha@andrew.cmu.edu or 412-287-2349 or Mike Kelley, CDFD Associate Director of Construction, at mdkelley@andrew.cmu.edu or 412-292-1300.
June 5 – June 9, 2023
· Ductbank install Traffic Impact
· Ductbank concrete pour
· Public storm excavation Noise Impact
· Parking closed off in front off in Phase 1A through 6/14/23 Traffic Impact
June 12 – June 16, 2023
· Continue yard storm and water line install
· Duct bank install
· RCP excavation Noise Impact
· Start forming curbs
· Public storm excavation Noise Impact
· Parking closed off in front off in Phase 1A through 6/14/23 Traffic Impact
· Mobilize and relocate fencing for Phase 1A.
On Wed, May 24, 2023 at 9:38 AM FMS's shutdown notice list for All Building Facility Coordinators <fmsfcc-all@lists.andrew.cmu.edu> wrote:UPDATE – Below is a 2-week look ahead for the work happening on Frew Street.
For any questions or concerns please contact Kevin Shaffer, CDFD Sr. Project Manager, at kevinsha@andrew.cmu.edu or 412-287-2349 or Mike Kelley, CDFD Associate Director of Construction, at mdkelley@andrew.cmu.edu or 412-292-1300.
May 22 – May 26, 2023
· Parallel parking available
· Road open to 1-way vehicle traffic
· Sidewalk detours in place Traffic Impact
· Private storm and water excavation
· Take delivery of storm piping
· Utility install – inside construction fence
· Parking closed off in front of in Phase 1A through 6/14/23 Traffic Impact
May 29 – June 2, 2023
· Continue private storm and water excavation Traffic Impact
· Start storm install
· Duct bank excavation Noise Impact
· Additional line striping Traffic Impact
· Parking closed off in front off in Phase 1A through 6/14/23 Traffic Impact
On Tue, May 2, 2023 at 10:58 AM FMS's shutdown notice list for All Building Facility Coordinators <fmsfcc-all@lists.andrew.cmu.edu> wrote:Facilities, Infrastructure and Risk Management (FIRM)
Facilities Management & Campus Services
TO: Shutdown Group, Facility Coordinators, Baker, Porter
FROM: Service Response Center
SUBJECT: Frew Street Summer Utility Improvement Project
Frew Street will be undergoing a utility improvement project which will impact the vehicular and pedestrian traffic this summer. The first phase of this project will be located adjacent to Porter Hall and Baker-Porter Hall. Underground utilities in this area will be installed under the campus sidewalk in 3 sub-phases. See the attached traffic control plan which outlines anticipated sub-phases.
As a part of this project, Frew Street will be reconfigured for one-way traffic with parallel parking to conform with the recently approved Institutional Master Plan. On May 15th and 16th Frew Street will be closed to all public traffic and parking. The street will be reopened on May 17th with one-way traffic running from Tech Street to Shenley Drive.
A temporary walkway on the park side of Frew Street will be installed with crosswalks while the campus sidewalk is removed for construction from May 17th through August 18th. The ADA parking outside of Baker-Porter Hall will be temporarily relocated during the summer.
At the end of the summer the campus sidewalk will be re-opened to pedestrian traffic, ADA parking will be restored, and Frew Street will remain as a one-way road with parallel parking. Phase 2 will take place summer 2024 between Baker Hall and Posner Hall.
For any questions or concerns please contact Kevin Shaffer, CDFD Sr. Project Manager, at kevinsha@andrew.cmu.edu or 412-287-2349 or Mike Kelley, CDFD Associate Director of Construction, at mdkelley@andrew.cmu.edu or 412-292-1300.
_______________________________________________
To manage your subscription to this mailing list, link to:
https://lists.andrew.cmu.edu/mailman/listinfo/fmsfcc-all_______________________________________________
To manage your subscription to this mailing list, link to:
https://lists.andrew.cmu.edu/mailman/listinfo/fmsfcc-all_______________________________________________
To manage your subscription to this mailing list, link to:
https://lists.andrew.cmu.edu/mailman/listinfo/fmsfcc-all