A preliminary planning meeting was held on Tuesday, 2/18, to discuss power outages needed to upgrade the switchgear in CIC (Robert Mehrabian Collaborative Innovation Center).  These upgrades will enable automatic power transfers during planned work.

This project will require three consecutive days of power outages:
5/16 from 10AM-6PM
5/17 from 6AM-6PM
5/18 from 6AM-6PM

Power will be restored at the end of each work period.


Emergency generators will be running if you have equipment on emergency power. 


CIC AND CIC GARAGE WILL BE CLOSED DURING THE OUTAGES.


Please contact Bob Penn, FMS Metering and Automation Systems Engineer, at 412-251-2658 or rpenn@andrew.cmu.edu for any questions or concerns regarding these shutdowns.