TO:  Shutdown Group, Gates Hillman

FROM:  Service Response Center

SUBJECT: Gates Hillman Center – Planned Power Shutdown Discussion 2/16 12PM

A full building power shutdown needs to be scheduled for the Gates Hillman Center (GHC) to replace a main switchboard circuit breaker.

A meeting has been set up to discuss details of this power shutdown on Monday, 2/16, at 12PM.  Please send an email to Shannon Wetzel at swetzel@andrew.cmu.edu if you would like to be invited to this meeting.

 
At this time, we are still awaiting confirmation of the shipment date of the new breaker and therefore do not yet have a guaranteed timeline for the work. The meeting is intended to explore constraints on when the full building outage can happen.

For any questions or concerns, please contact Joe Yimin, CDFD Sr. Project Manager, at 
jyimin@andrew.cmu.edu or 412-427-0721.