Fri. Jul 24th, 2026

Facilities, Infrastructure and Risk Management (FIRM)

Facilities Management Services

 

TO:  Shutdown Group, CUC

FROM:  Service Response Center

SUBJECT: CUC Loading Dock Brick Repair 7/27 7AM-4PM


There will be exploratory work for the CUC loading dock brick repair project on Monday, July 27, from 7AM to 4PM. Repairs will be made to three exterior brick walls near the loading dock service entrance.

A crane will be on site to support the work. The loading dock will remain accessible for deliveries, and work can be temporarily paused as needed. However, the double doors must remain closed whenever overhead work is taking place.

There will be moderate noise and intermittent construction activity.

Please see the attached plan showing the work area.

If you have any questions or concerns, please contact Jan Held, CDFD Principal Project Manager, at jheld@cmu.edu.