SUBJECT: Warner Hall Elevator Replacement Update

 

With 4 weeks down and 2 to go, we are happy to announce that the Warner Hall Elevator Replacement Project is continuing to go well and remain on schedule! 

 

What’s Next?

          The elevator’s fire alarm recall system will be tested this Thursday, 6/29. 

          The elevator is scheduled to be inspected next Thursday, 7/6.

 

 

As a thank you for your patience, people with assigned spaces in Warner Hall had the opportunity to win a 2017 NHL Stanley Cup Champions Shirt.  Congratulations to the following winners:

 

          Floor 2 – Letty Macioce

          Floor 3 – Lindsay Pelz Luciano

          Floor 4 – Michelle Martin

          Floor 5 – Joanna Dickert

          Floor 6 – Emily Meyer

 

Please continue to reach out to Shannon Wetzel (swetzel@andrew.cmu.edu) or Lenny Libbon (ll1r@andrew.cmu.edu) with questions, comments or noise concerns.