Fri. Jan 2nd, 2026

Division of Operations

Facilities Management and Campus Services

 

TO:  Shutdown Group, Porter Group

FROM:  Service Response Center

SUBJECT:  ANSYS Building Site Verification 9/30

 

Beginning Saturday, September 30th from 6am through 5pm, CDFD will be conducting Geotechnical site verifications for the ANSYS Simulation Building and Undergraduate Maker Center. It is anticipated that the work will be completed over the weekend on the future site of the ANSYS building on the sidewalk behind the construction trailer in front of Porter Hall. The work consists of removing and replacing a portion of sidewalk. Pedestrians and vehicular traffic will be able to pass through the area unaffected.  One air handler in Porter Hall will be turned off from 6:00 AM to 10:00 AM effecting air make-up to the B-Level of Porter Hall. The fan coil units in that area will remain operational. This only effects the make-up air.

 

If you have any questions or concerns, please call Jennifer McDowell

at 83763 or email jmcdowell@cmu.edu