UPDATE – The following areas in Hamerschlag Hall will be affected from this power outage:

 

          C-level/MechE areas

          C-101

          A-300 wing

          1300 wing

          1100 wing

          2100 wing

 

 

From: FMS Announce
Sent: Wednesday, October 18, 2017 1:28 PM
To: ‘fms-shutdown@lists.andrew.cmu.edu’ <fms-shutdown@lists.andrew.cmu.edu&gt;; ‘fms-hamerschlag@lists.andrew.cmu.edu’ <fms-hamerschlag@lists.andrew.cmu.edu&gt;
Subject: Hamerschlag Hall Power Shutdown 10/21

 

Division of Operations

Facilities Management and Campus Services

 

TO:  Shutdown Group, Hamerschlag Hall

FROM:  Service Response Center

DATE:  October 18, 2017

SUBJECT:  Hamerschlag Hall Power Shutdown 10/21

 

There is a planned power outage scheduled for Hamerschlag Hall on Saturday, 10/21, from 6:00AM – 2:30PM.  This outage is necessary while electrical work is being done for the Maker Wing Project. 

 

The men’s and women’s restrooms will be affected during this shutdown, along with various outlets throughout the building and baseboard heating.  The elevator will still be operational during this shutdown. 

 

Please check all critical equipment and contact FMCS at fixit@andrew.cmu.edu or 8-2910 to request temporary power.

 

For any construction related questions or concerns, please contact CDFD Project Manager, Mike Kelley, at 412-268-2366 or mdkelley@andrew.cmu.edu.