Wed. Jan 28th, 2026

Division of Operations

Facilities Management and Campus Services

 

TO:  Shutdown Group, Cohon University Center

FROM:  Service Response Center

DATE:  December 11, 2017

SUBJECT:  Cohon University Center Scheduled Work 12/23 – 1/2

 

The following work is scheduled to be completed at the Cohon University Center between 12/23 – 1/2:

 

          The ceilings in the men’s, women’s and family shower rooms in the fitness center will be painted.  Access to these areas will be closed during this time.

          The pool deck is scheduled to be pressured washed.

          The broken tiles on the floor of the men’s shower room, closest to the pool, will be replaced.

          The women’s locker room will be closed on 12/22 from 9:30AM until 11:30AM while the dryer vent is being cleaned.

 

If you have any questions or concerns, please contact Ralph Hilbert at FMS 412- 268 6147.