The following work is scheduled to be completed at the Cohon University Center between 12/23 – 1/2:
– The ceilings in the men’s, women’s and family shower rooms in the fitness center will be painted. Access to these areas will be closed during this time.
– The pool deck is scheduled to be pressured washed.
– The broken tiles on the floor of the men’s shower room, closest to the pool, will be replaced.
– The women’s locker room will be closed on 12/22 from 9:30AM until 11:30AM while the dryer vent is being cleaned.