UPDATE – The brief power outage that was scheduled to happen this morning has been cancelled. A notice will be sent out when this has been rescheduled.
From: FMS Announce
Sent: Thursday, January 11, 2018 9:19 AM
To: ‘fms-shutdown@lists.andrew.cmu.edu’ <fms-shutdown@lists.andrew.cmu.edu>; ‘fms-fmsb@lists.andrew.cmu.edu’ <fms-fmsb@lists.andrew.cmu.edu>; ‘fms-newelsimon@lists.andrew.cmu.edu’ <fms-newelsimon@lists.andrew.cmu.edu>; ‘fms-hamburg@lists.andrew.cmu.edu’ <fms-hamburg@lists.andrew.cmu.edu>; ‘fms-smith@lists.andrew.cmu.edu’ <fms-smith@lists.andrew.cmu.edu>
Subject: REMINDER – Brief Power Shutdown 1/8 & 1/12
REMINDER – The FMS Building, Newell Simon, Hamburg and Smith Halls will experience a momentary loss of power on Friday morning, 1/12, between the hours of 6:00AM and 7:00AM. Buildings may be affected for up to 15 minutes.
From: FMS Announce
Sent: Friday, January 5, 2018 10:55 AM
To: ‘fms-shutdown@lists.andrew.cmu.edu’ <fms-shutdown@lists.andrew.cmu.edu>; ‘fms-fmsb@lists.andrew.cmu.edu’ <fms-fmsb@lists.andrew.cmu.edu>; ‘fms-newelsimon@lists.andrew.cmu.edu’ <fms-newelsimon@lists.andrew.cmu.edu>; ‘fms-hamburg@lists.andrew.cmu.edu’ <fms-hamburg@lists.andrew.cmu.edu>; ‘fms-smith@lists.andrew.cmu.edu’ <fms-smith@lists.andrew.cmu.edu>
Subject: REMINDER – Brief Power Shutdown 1/8 & 1/12
REMINDER – The FMS Building, Newell Simon, Hamburg and Smith Halls will experience a momentary loss of power on Monday morning between the hours of 6:00AM and 7:00AM. Buildings may be affected for up to 15 minutes.
From: FMS Announce
Sent: Thursday, January 4, 2018 12:15 PM
To: fms-shutdown@lists.andrew.cmu.edu; ‘fms-fmsb@lists.andrew.cmu.edu’ <fms-fmsb@lists.andrew.cmu.edu>; ‘fms-newelsimon@lists.andrew.cmu.edu’ <fms-newelsimon@lists.andrew.cmu.edu>; ‘fms-hamburg@lists.andrew.cmu.edu’ <fms-hamburg@lists.andrew.cmu.edu>; ‘fms-smith@lists.andrew.cmu.edu’ <fms-smith@lists.andrew.cmu.edu>
Subject: Brief Power Shutdown 1/8 & 1/12
Division of Operations
Facilities Management and Campus Services
TO: Shutdown Group; FMSB; Newell Simon; Hamburg, Smith
FROM: Service Response Center
DATE: January 4, 2018
SUBJECT: Brief Power Shutdown 1/8 & 1/12
There will be a momentary loss of power, about 5 minutes long, to the buildings listed below sometime between 6:00AM and 7:00AM on Monday, 1/8, in order to make the power connects to the FMS switchgear for the Tepper Quad project:
– The FMS Building
– Newell Simon Hall
– Hamburg Hall
– Smith Hall
There will be an additional momentary loss of power on Friday, 1/12, between 6:00AM and 7:00AM.
Please contact Lenny Libbon with any questions or concerns at x8-6148 or email LL1R@andrew.cmu.edu.