Sun. Jan 25th, 2026

UPDATE –  Due to the Inauguration Events on campus last week, the below work at the Alumni House was rescheduled to begin today, 10/29.  This work is scheduled to be completed by Monday, 11/12.

 

 

From: FMS Announce
Sent: Wednesday, October 17, 2018 7:43 AM
To: ‘fms-shutdown@lists.andrew.cmu.edu’ <fms-shutdown@lists.andrew.cmu.edu&gt;
Subject: Alumni House Porch and Rear Roof Replacements 10/22 – 11/5

 

Division of Operations

Facilities Management and Campus Services

 

TO: Shutdown Group

FROM:  Service Response Center

SUBJECT: Alumni House Porch and Rear Roof Replacements 10/22 – 11/5

 

The front porch roof and lower rear roofs of the Alumni House are scheduled to be replaced starting on Monday, 10/22.  This work should be completed by Monday, 11/5. 

 

The equipment needed for this project will be set up tomorrow, 10/18.

 

Access to the Alumni House will remain open during this work.

 

There will be some noise and fumes associated with this project.

 

Please contact Lenny Libbon at x8-6148 or LL1R@andrew.cmu.edu with any questions or concerns regarding the roof replacements at the Alumni House.