Division of Operations
Facilities Management and Campus Services
TO: Shutdown Group, Facility Coordinators, CUC
FROM: Service Response Center
DATE: May 17, 2019
SUBJECT: East/West Walkway Concrete Work
Replacement of a portion of the concrete sidewalk at the East/West walkway will begin on Monday, 5/20, and is expected to be completed by the end of June, depending on the weather.
This work will be broken into two phases:
– The first phase will begin where the replacement stopped last year. Pedestrian traffic will be routed to the new sidewalk that was installed during last year’s phase of work.
– The second phase will be the large section of concrete in front of the Merson Courtyard. Pedestrian traffic will be routed as shown on the below overhead view with a temporary walkway on the East side and sidewalk on the West side.
The Merson Courtyard will remain open during this work.

Please contact Ron Cunningham for any questions or concerns regarding the concrete work on the East/West walkway at x8-1556 or rcunning@andrew.cmu.edu.