Division of Operations
Facilities Management and Campus Services
TO: Shutdown Group, Housing, Morewood
FROM: Service Response Center
DATE: July 15, 2019
SUBJECT: Power Shutdown Discussion Meeting 7/16 10:30AM
There will be a meeting on Tuesday, 7/16, at 10:30AM to discuss an upcoming power shutdown that will affect Morewood Gardens, Morewood E Tower and Stever House. The location of the meeting will be sent later today. This power shutdown is necessary in order to install a new circuit breaker as a part of the Morewood E Tower temporary electrical service replacement project.
The intent of the meeting is to solicit input on the potential impacts to critical equipment that would be affected and determine a date/time that avoids or minimizes the most negative effects.
Please send an email to Shannon Wetzel at swetzel@andrew.cmu.edu if you plan to attend this meeting.