Division of Operations
Facilities Management and Campus Services
TO: Shutdown Group, CFA
FROM: Service Response Center
SUBJECT: CFA South Entrance Masonry work 9/3 – 9/20
The College of Fine Arts building is scheduled to have masonry restoration work done on the South entrance, adjacent to the Peace Garden, between 9/3 and 9/20.
This work includes some minor brick repointing and replacement, resetting some granite paver stones and sealing the joints. The steel lintel and utility space doors will also be replaced on the underside of the entrance.
One section of the stairway will be closed at a time for this work and one will remain open.
For questions or concerns regarding this work, please contact Ron Cunningham at rcunning@andrew.cmu.edu or x8-1556.