Thu. Jan 22nd, 2026

Division of Operations

Facilities Management and Campus Services

 

TO:  Shutdown Group, CIC

FROM:  Service Response Center

SUBJECT: CIC Driveway Obstruction 12/6

 

 

Campus Design & Facility Development is working with a contractor to renovate the lower level tenant space of the Robert Mehrabian Collaborative Innovation Center (CIC).  A box truck will be parked in driveway of the CIC Friday morning, 12/06, limiting the traffic to a single lane in this area.  Cones will be placed around the vehicle to identify caution.  Hoses will also be stretched from the truck, across the sidewalk, into the window of the CIC.  The hoses will be placed under a ramp or stretched overhead so to not obstruct the public walkway.  This brief inconvenience will last about 3 hours and is needed to facilitate a construction process.

 

If you have any questions regarding this work, please contact CDFD Associate Director, Chris Conroy, at 8-3879 orcconroy@andrew.cmu.edu.