Facilities, Infrastructure and Risk Management (FIRM)
Facilities Management & Campus Services
TO: Shutdown Group, CUC group
FROM: Service Response Center
DATE: July 23, 2020
SUBJECT: CUC/Gesling Stadium sidewalk repairs- July 23-31
Eisler Landscapes will begin concrete repair work on the University Center east entry adjacent to Gesling Stadium tomorrow July 23-July 31st. They will be removing a portion of the sidewalk and replacing concrete at the stairs to the entry rotunda—the east entry to the CUC will need to remain closed for the duration of this work.
Any questions or concerns, please contact Jenn Rogers at jlrogers@andrew.cmu.edu or 412-268-1964
/var/folders/tt/7lstk3_d4kj6h_gz2rvc5ch5b8yg7_/T/com.microsoft.Outlook/WebArchiveCopyPasteTempFiles/cidimage001.png@01D66010.FA88C960“>