SUBJECT: Wean Hall Exhaust Upgrades Project – Discussion Meeting 8/20 10AM

 

Campus Design & Facility Development (CDFD) is working with Facilities Management & Campus Services(FMCS) on the Wean Hall Exhaust Upgrades Project this Fall. The project scope includes replacing the laboratory exhaust fans at Wean Hall with a new system.

This project entails erecting a crane at the hairpin turn of Hamerschlag Drive in order to lift the supporting steel structure and the mechanical equipment.

 

The project team would like to review the logistics plan and discuss the schedule for this activity with the impacted campus community partners over Zoom on Thursday, 8/20, from 10:00AM-11:00AM.  Please send an email to Shannon Wetzel at swetzel@andrew.cmu.edu if you would like the Zoom meeting added to your calendar.

 

Please contact Chris Conroy cconroy@andrew.cmu.edu or Salonika Garapaty sgarapat@andrew.cmu.edu with any questions or concerns regarding this project.