Fri. Jan 16th, 2026

Facilities, Infrastructure and Risk Management (FIRM)

Facilities Management & Campus Services

 

TO:  Shutdown Group, Facility Coordinators

FROM:  Service Response Center

DATE:  April 22, 2022

SUBJECT: Spring 2022 Campus Roofing Inspection Schedule  

 

Below is the Spring 2022 Roofing Inspection Schedule for Campus.  The dates listed are subject to change, due to weather conditions.

 

Please contact Lenny Libbon with any questions or concerns regarding this schedule at 412-268-6148 or email LL1R@andrew.cmu.edu.

 

MONDAY 05/02/22     

5120 Holyrood (New President’s House)

           

TUESDAY 5/03/22  

WARNER HALL – Main
CYERT HALL – All                                   

CIC – ALL     

HAMERSCHLAG HALL

          Main Roof-Main Tower

          Main-Metal and Tee Wings

          South Roof-Modified Green

          North-B-Level

          North-D-Level

ROBERTS HALL – All

SCOTT HALL – All

EAST CAMPUS GARAGE

          Elevator

          Stairwell

          Press Box

ALUMNI HOUSE – All

BRAMER HOUSE AND GARAGE – All

TEPPER

4609 WINTHROP

203 S. CRAIG

 

WEDNESDAY 5/04/22   

POSNER CENTER – All

HUNT LIBRARY – Main

SMITH HALL – All

HAMBURG HALL – Main

NEWELL-SIMON HALL – Roofs 1-6

PHYSICAL PLANT/MATH BUILDING – All

MELLON INSTITUTE

          5th and 6th Floors

          7th Floor

          8th Floor

          9th Floor

                                   

THURSDAY 5/05/22      

COLLEGE OF FINE ARTS – All

MARGARET MORRISON

          Main and Rotunda

          L & R Third Floor Lower Concourse

          Intelligent Building

POSNER HALL

          A-B Roofs

          C-D Roofs

          E-G-I Roofs

          F-Roof

300 S. CRAIG – All

UTDC – 4516 HENRY

INI -4616 HENRY

GATF BLDG – 4615 FORBES AVE

I I I – OLD BANK BUILDING

 

FRIDAY 5/06/22

WEAN HALL

          Roofs A-B-F-H

          Roofs C-D-E-G

          Roofs K-L-M

DOHERTY HALL

          Main and Tee Wings

          A-Level Upper

          A-Level Scanning Lab

          C-Level Roof

          Phase 1 Infill Roof

PURNELL CENTER – All

GATES/HILLMAN BLDG

SEI – All

SEI – Garage Roof

407-409 S. CRAIG – All

205 S. CRAIG 

4612 HENRY

4618 HENRY

4620 HENRY

4721 FIFTH AVE

 

MONDAY 5/09/22        

ANSYS HALL

PORTER HALL

          Main

          B-Level Roofs

          Roofs Above 220 Area

BAKER HALL – Main and Tee Wings

COHON UNIVERSITY CENTER

          Metal

          Flat

ETC (formerly PTC) – All

6555 PENN AVE – All

WHITFIELD HALL

          Main

          Lower Flat Roofs

          477 MELWOOD AVE- All