Facilities, Infrastructure and Risk Management (FIRM)
Facilities Management & Campus Services
TO: Shutdown Group, Newell Simon, FMS, CIC, Hamburg, Smith
FROM: Service Response Center
SUBJECT: Fire Hydrant Replacement Exterior of NSH 9/19
A leaking Fire Hydrant located at the northwest corner of the exterior of Newell Simon Hall is scheduled to be replaced on Monday, 9/19.
There will be excavation equipment in this area so please be cautious of the work area, as noted in the attached image. The drive area will be closed for vehicle traffic at this location during work, but will be open for emergency use if needed. Pedestrian traffic will be restricted slightly near the work area, but open along Hamburg and Smith Hall.
Parking at the CIC garage will not be impacted.
Please contact Ron Cunningham, FMS Principal Project Manager, at rcunningham@andrew.cmu.edu for any questions or concerns related to this work.
.

