REMINDER – The steam shutdown for the Highmark Center for Health, Wellness and Athletics construction project is scheduled for this Saturday, 9/24, and Sunday, 9/25. 

 

This work will impact CFA, Posner Center, Posner Hall, CUC, Donner, Hill Dorms, MMCH, Resnick, and West Wing.  Please see the below notice for more details.

 

For questions or concerns regarding this shutdown, please contact Ralph Hilbert, FMS Zone Supervisor, at 412-527-5604.

 

On Fri, Sep 9, 2022 at 5:37 AM FMS Announce <fmsannc@andrew.cmu.edu> wrote:

UPDATE – The postponed steam outage for The Highmark Center for Health, Wellness and Athletics construction has been scheduled for Saturday, 9/24, to Sunday, 9/25.  As a reminder, the outage will be two phases with Phase 1 starting at 6AM Saturday and Phase 2 starting at 6AM Sunday.  All work will be completed by 6PM Sunday.

 

This work will impact CFA, Posner Center and Posner Hall for the first phase with steam restored to these buildings Saturday evening.  The remaining buildings – CUC, Donner, Hill Dorms, MMCH, Resnick, and West Wing – will experience the full duration.


For questions or concerns regarding this shutdown, please contact Ralph Hilbert, FMS Zone Supervisor, at 412-527-5604.

 

 

POSTPONED – Steam Shutdown Affecting Multiple Buildings – 8/26 & 8/27

Inbox

 

FMS Announce <fmsannc@andrew.cmu.edu> (sent by swetzel@andrew.cmu.edu)

Thu, Aug 25, 9:30 AM

to fms-shutdown@lists.andrew.cmu.edufms-uc@lists.andrew.cmu.edufms-mmch@lists.andrew.cmu.edufms-housing@lists.andrew.cmu.edu

UPDATE – The 48 hour steam shutdown scheduled for this Friday, 8/26, and Saturday, 8/27, has been postponed until a later date.   An updated notice will be sent when the shutdown is rescheduled.

 

 

Facilities, Infrastructure and Risk Management (FIRM)

Facilities Management & Campus Services

 

TO:  Shutdown Group, CUC, MMCH, Housing

FROM:  Service Response Center

DATE:  August 15, 2022

SUBJECT: Steam Shutdown Affecting Multiple Buildings – Discussion Meeting 8/19 1PM

 

The Highmark Center for Health, Wellness and Athletics would like to schedule a 48 hour steam shutdown that will affect the following buildings:

          Margaret Morrison Carnegie Hall

          Donner & Hill Dorms

          West Wing & Resnik

          Cohon University Center

The reason for this shutdown is to connect the building to the campus steam distribution system.  The targeted date for this shutdown is tentatively scheduled for 8/26 – 8/27. 

There will be a ZOOM meeting on Friday, 8/19, at 1PM to discuss the details of this shutdown. 

Please send an email to Shannon Wetzel at swetzel@andrew.cmu.edu if you would like to be invited to this meeting.

 