Wed. Jan 14th, 2026

Facilities, Infrastructure and Risk Management (FIRM)
Facilities Management & Campus Services

 

TO:  Shutdown Group, Hamerschlag Hall

FROM:  Service Response Center

SUBJECT: Hamerschlag Hall Chilled Water Shutdown

 

The chilled water system in Hamerschlag Hall will be shut down starting today, 11/14,  to consolidate new chilled water bridges in conjunction with the F Level construction project.   

 

The mechanical systems will be modified to utilize the colder temperatures to ensure building temperatures are kept in the same range through the building.  The heating system will not be affected by this chilled water shutdown.  Drawings are attached that show which areas are affected.   

 

The chilled water system will be back on line by Friday, 11/18.     

 

If you are in an area in the building that is experiencing warmer than normal temperatures, please contact CDFD Project Manager, Jan held, at jheld@cmu.edu or 412 527 5627.